The wood trim on units 44-28 will be complete by early next week, pending final deficiencies.
Staining of shakes on units 44-28 will begin next week, starting at unit 28 and working up.
Units 1-12 will be washed throughout next week, and painting of the wood trim on these units will also commence next week.
-Operations